Construction Hours for Rancho Vista Project

The developer shall limit all construction work to occur only between the hours of 7:30 a.m. to 6:00 p.m. on the days of the week of Monday through Friday, and the hours of 9:00 a.m. to 6:00 p.m. on Saturdays. The developer shall perform no construction work at any hours on Sundays.

Also, the developer shall limit all construction work involving exceptionally loud noises, vibratory equipment, trucks backup devices, and gas powered compaction tools to occur only between the hours of 8:30 a.m. to 4:00 p.m. on the days of the week of Monday through Friday, and the hours of 9:00 a.m. to 4:00 p.m. on Saturdays. The developer shall perform on construction work at any hours on Sundays.